Down Lane Park Improvement  logoDown Lane Park Improvement

Milestones

  • Forming the Community Design Group

    December 2021

     

    -

     

    January 2022

    Bringing together 10 representatives from the local community, from a range of interest groups: community groups, active travel, youth, residents' association, sports clubs, park user groups, disability + Cllrs Ruth Gordon and Mike Hakata, Cabinet Leads for Placemaking and Co-designing green spaces.
  • Laying the foundations of co-design

    February 2022

     

    -

     

    May 2022

    Council and Community Design Group coming together; agreeing Terms of Reference; Design by Consensus capacity building workshop; understanding opportunities & constraints; walkabout of the park, study visits to other London parks
  • Co-design: Park concept designs (Options 1 & 2)

    May 2022

     

    -

     

    September 2022

    Five design workshops with (landscape architectural) design team; exploring uses and locations; prioritisation; focus on play, maintenance, and costs; group and round table discussions
  • Public Engagement # 1

    3rd October 2022

     

    -

     

    23rd October 2022

    In person engagement event 11.00-4.00pm, Sat 8th October at Living Under One Sun in Down Lane Park; In person engagement event 3.30 -7.00pm, Thurs, 13th October at Mitchley Road Hall; In person 'pop up' engagement event 10.30am - 1.00pm, Sat, 22nd October in Down Lane Park; 3rd - 23rd Oct, outdoor public exhibition of engagement boards and design options by the Tennis Courts in Down Lane Park; 3rd - 23rd October, engagement on-line survey on Commonplace
  • Independent Design Review # 1

    19th October 2022

     

    -

     

    19th October 2022

    Independent design scrutiny and advice from Urban Design London's Environmental Design Review Panel, supported by the Mayor of London's Green & Resilient Spaces Fund.
  • Co-design: Park (detailed) & Community Hub (concept) design

    October 2022

     

    -

     

    May 2023

    Three design workshops with (landscape + building architectural) design team; developing preferred design option for the park; and exploring location, function and form of Community Hub building; focus on play, maintenance, and costs; group and round table discussions
  • Public Engagement # 2

    15th May 2023

     

    -

     

    28th May 2023

    A mix of in-person and on-line engagement activity seeking feedback on a single 'preferred' design option for the park and options for a permanent Community Hub building
  • Independent Design Review # 2

    17th May 2023

     

    -

     

    17th May 2023

    Independent Design review from Haringey Council's Quality Review Panel
  • Assessing cost, affordability & equality

    June 2023

     

    -

     

    Oct 2023

    Calculating the cost of designs and optimising both design and cost; assessing the affordability of the Community Hub building; assessing the equalities impact of preferred designs
  • Planning Application & Planning Authority decision

    November 2023

     

    -

     

    February 2024

    Submit Planning Application to Local Planning Authority seeking approval for proposed designs; approximate 10-12 week consideration period; Local Planning Authority 'determination' to grant or refuse; Planning Applications Committee 5th February 2024
  • Detailed Construction Design (Phase 1 works)

    September 2023

     

    -

     

    December 2023

    Preparation of detailed construction design drawings for Phase 1 of Works Programme
  • Delivery (Construction) Phase 1 Improvement Works

    15th January 2024

     

    -

     

    June 2024

    new and enhanced, wider and resurfaced pathways, supportive user comfort and active travel tree, meadow, and under planting, supporting habitat creation and biodiversity Sustainable Urban Drainage (SuDS) basins and improved drainage, supporting climate change resilience canopy lifting, new lighting, and better natural surveillance, supporting improved safety new and improved entrances, supporting improved safety, connectivity, and access
  • Construction Design (Phases 2-4)

    November 2023

     

    -

     

    February 2024

    Detailed construction design of remaining phases of the landscape masterplan and Community Hub building, including café and garden; Cost Planning; optimising costs and designs
  • Start on Site: Phase 2 Improvement Works

    June/July 2024

     

    -

     

    May/June 2025

    Construction of Phase 2 of the park improvement works, including Community Hub building, café and garden